According to the EIA Regulation, a project related to the underground exploitation of mineral resources may be subject to an EIAS. In such a case, the impact assessment procedure consists of the following stages:
-
deciding on the need for impact assessment;
-
determining the scope and content of the EIAS;
-
decision approving or rejecting the EIAS.
The developer should ask from the Ministry of Environmental Protection, or the Provincial Secretariat in charge of environmental affairs when the mining activities are performed in AP Vojvodina, to decide whether the environmental impact assessment is required i.e. whether the EIAS should be prepared. The Ministry (Provincial Secretariat) informs the public and interested entities on the submitted application within 10 days so comments and opinions regarding the application may be submitted within 10 additional days. The competent authority shall render its decision within 15 days following expiry of the deadline for the submission of comments and opinions, which will include the specifics of the project and the location, as well as the submitted opinions. There is no unconditional obligation for preparing EIAS for mining projects. Therefore, if the competent authority decides that an environmental impact assessment is not required, it may determine the minimum environmental protection requirements, in accordance with separate regulations.
In case the competent authority decides that an EIAS is required, the developer shall submit a request to the competent authority to determine the scope and content of the EIAS. The EIA Act stipulates the mandatory elements of each EIAS while the Ministry of Environmental Protection prescribes its content in more detail. The procedure and the deadlines (except the opinion submission deadline which lasts 15 days) are the same as for the procedure for deciding whether the environmental impact assessment (i.e. EIAS) is required or not.
Finally, the developer is required to prepare the EIAS according to the scope and content as determined by the competent authority and to submit it within one year the date when the scope and content of the EIAS have been determined. The competent authority shall make the EIAS available for public viewing, organize a presentation about it, and conduct public consultations on the EIAS. After that, the EIAS shall be submitted to the specially formed (one or more) Technical Commission to examine it. Ministry shall approve or reject the EIAS based on the Technical Commission's report.
Additionally, the Mining Act provides for licenses for performing specific activities in geological explorations and exploitation. According to the Mining Act, a license for environmental protection activities in the exploitation of mineral resources is required by private individuals in the field of mining. Licensing eligibility criteria include:
-
the appropriate qualifications;
-
authorization to carry on environmental protection activities;
-
five years of working experience in the respective positions.