The European Commission may approve the concentration either after a phase I assessment or after a phase II assessment. (i) Simple assessment (Phase I assessment)
Examination by the European Commission: Maximum 25 working days from reception of a complete notification (“Initial Period”). In practice, it is highly recommended – save in very straightforward cases – to file an informal “pre-notification” in order to ensure that the notification will be considered complete on the day of its official filing.
Commitments (also called “remedies”): If commitments are presented to the European Commission, the Initial Period is extended by 10 extra working days.
Stop-the-clock: At the initiative of the European Commission, when the notifying party (a) fails to inform the EC of a new relevant and material fact, or (b) fails to provide the requested information within the allocated time. The running of the clock resumes as soon as the cause justifying the suspension has disappeared.
At the end of Phase I, the European Commission can either:
- find that the transaction is not subject to the European Merger Regulation (rare);
- approve (clear) the transaction - without conditions (approximately 90% of cases);
- approve (clear) the transaction - with conditions (approximately 5% of cases) or,
- open a “Phase II,” thereby initiating an in-depth investigation, if serious doubts remain about the anti-competitive effects of the transaction (approximately 5% of cases)
Possible intervention of National competition authorities (NCAs): The NCAs have 15 working days from the beginning of phase I to request a referral if a concentration affects or significantly threatens to significantly affect competition within their Member State.
(ii) In-depth assessment (Phase II assessment)
Examination by the European Commission: between 90 and 125 working days from the opening of phase II.
Commitments: If commitments (or modifications of previously transmitted commitments) are presented to the European Commission after 55 working days of the phase I assessment, the assessment period is extended by 15 extra working days, in the limit of 105 working days from the beginning of phase II.
Suspension requested by the parties: The parties may ask for a suspension for no longer than 20 working days, mainly to finalize their commitments.
Stop-the-clock: At the initiative of the European Commission, when the notifying party (a) fails to inform the EC of a new relevant and material fact, or (b) fails to provide the requested information within the allocated time. The running of the clock resumes as soon as the cause justifying the suspension has disappeared.